Planned Maintenance of Colocation Router Software Upgrade - Wellington - 26/07/2020
Scheduled Maintenance Report for Telesmart Ltd
Completed
The scheduled maintenance has been completed.
Posted Jul 27, 2020 - 02:00 NZST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 26, 2020 - 22:00 NZST
Scheduled
Telesmart would like to inform you that there will be an outage to some network, internet and voice services on this date during times specified below.

Reason for Work: Colocation Router Software Upgrade - Wellington.
Impact Expected: During the planned work window impact expected 1x up to 5min break in service.
Services Impacted: Interruption on Internet and Voice services.
Impacted Service Area: Wellington, Lower North Island, South Island

NZ Time : 2020-07-26 22:00 NZST - 2020-07-27 02:00 NZST
AEST Time : 2020-07-26 20:00 AEST - 2020-07-27 00:00 AEST

Please do not hesitate to contact us if you have any questions.
Posted Jul 20, 2020 - 12:25 NZST